+44 (0)28 92 636858 [email protected]

A big milestone at Queen Elizabeth Hospital in London this week for PM POWER, with the first delivery of new plant to site.

The 6no 28,000Litre steel, double skin, structural bulk fuel tanks, which are designed and purpose built to directly support the generators and the acoustic enclosures above, were offloaded and positioned in the basement of the new Energy Centre.

With the tanks skated onto a temporary platform at ground level and then lowered 2 metres into the basement, it was a busy week for our lift & shift specialist contractor and the PM POWER installation team.

 

 

Share This